Removal of old environmental burden in Jaroměř
Phase 1 of the Remediation Intervention at the Scrap Yard Site Owned by KD METALL s.r.o.
Client: KD METALL s.r.o.,
IČ 47471697
Country: Czech Republis
Implementation period: 04/2022 - on goin
Contract value: 8,454 mil Kč
More about the project
The site, formerly home to a Benzina s.p. distribution warehouse, is located on the southwestern outskirts of Jaroměř in the Náchod district. The remediation intervention focused on the removal of contamination by petroleum substances and benzene, which was present in building structures, soil, and groundwater.
During the remediation process, excavation, transportation, and disposal of excessively contaminated soil were carried out, totaling 5,740 tons. Additionally, four single-walled underground steel fuel tanks were removed. The work also included the installation of a DN200 remediation drain approximately 53 meters long, placed at a depth of 3 meters. To ensure continuous monitoring of the remediation process, a monitoring system for soil, building structures, and groundwater was implemented.
We provided
- Demolition of the storage hall and paved areas
- Execution of soldier pile shoring to secure the remediation excavation (50 meters in length)
- Execution of the remediation excavation covering 2,616 m² to a depth of 3–5 meters
- Pumping of groundwater contaminated with petroleum substances from the remediation excavation
- Remediation work
- Monitoring
Are you working on a similar project and could use our services?
Fill out a simple form and we will get back to you within 24 hours.
You can also reach us on the phone: +420 235 522 252