Restoration of the pond in Hůrka
Restoration of the existing pond in the village of Hůrka.
Client: Municipality of Velke Popovice
Komenskeho 254, 251 69 Velke Popovice
Country: Czech Republic
Implementation period: 8/2017 - 12/2017
Completion date: October 2017
Contract value: 38,240 $
More about the project
The restoration of the existing pond involved the removal of sediment, the construction of a small dam for the littoral zone, the removal of original functional structures, and the installation of a new inlet and safety overflow, including their connection to the existing piping system. The project also included the reclamation of the pond’s banks.
We provided
- Water drainage
- Monitoring of protected species presence
- Sediment removal
- Earthworks for the construction of the new dam for the littoral zone
- Removal of the old inlet and installation of a new inlet and drainage pipe with connection to the existing system
- Construction of a new safety overflow
- Planting of new trees
Are you working on a similar project and could use our services?
Fill out a simple form and we will get back to you within 24 hours.
You can also reach us on the phone: +420 235 522 252
or via e-mail at info@dekonta.cz